Project Highlights

Personnel on Site: 110
Manhours: 390,000
Concrete poured: 23,200m3
Total reo placed: 3,200T

Project Details

Centrals were engaged by Crushing Services International (a subsidiary of Mineral Resources Limited (MRL)), to execute the work package for the placement of all concrete and installation of cast in embedments. This included the supply and placement of all formwork and reinforcing
the concrete for the following structures:

  • Primary, secondary, and tertiary crushing stations
  • Dry screening station
  • Plant conveyor systems
  • Fines product stacker
  • Three (3) flotation circuits including thickener tanks, ball mills, storage shed slabs, substations, pipe and cable racks, and water storage tanks
  • Workshops – including light vehicle, heavy vehicle, and warehouses

Wodgina Mine Site Concrete Works

Project Details

Client: Crushing Services International

Location: Wodgina Mine Site, Pilbara, WA

Duration: 20 months

Completion: September 2019

Value: $33.5M